How to Evaluate IT Projects and Avoid Double Deadlines
🌐 Machine-translated from Russian. Show original
"We'll do it in two weeks" — and two months later the project is still running. Mistakes in the estimates are almost always the same. Let's figure out how to avoid them.
In this part:
Why Grades Lie#
- They only evaluate the code, forgetting about analysis, tests, reviews, deployments, documentation, and approvals.
- They are evaluated under ideal conditions: no vacations, illnesses, urgent tasks, or meetings.
- Uncertainty at the beginning is huge: at the start, the actual timeframe can differ from the estimate several times. As requirements are refined, the range narrows — so the estimate needs to be revised.
Decomposition#
The main tool: break the work down until each task is no more than 1–2 days. "Weekly" tasks are uncertainty, not evaluation.
Don't forget the tasks that are not visible in the TS:
- setting up the environment and CI;
- data migration and transfer;
- integrations and testing them with the other side;
- user training and documentation;
- post-launch stabilization.
Three-point assessment (PERT)#
For each problem, there are three numbers: the optimistic (O), the most likely (M), and the pessimistic (P) estimate.
Expected time = (O + 4M + P) / 6
| Problem | O | M | P | Expected |
|---|---|---|---|---|
| Registration form | 1 | 2 | 5 | 2.3 days |
| Integration with payments | 2 | 4 | 12 | 5 days |
| Sales report | 1 | 1.5 | 3 | 1.7 days |
The big difference between M and P is a risk signal: clarify such tasks first.
Evaluation by the team#
- Planning poker: everyone evaluates independently, then discusses discrepancies. A multiplicity means people understand the task differently.
- The one who will do it is evaluated, not the manager for them.
Buffer and calendar#
- Convert ideal days into calendar days: a developer usually has 5–6 productive hours a day, not 8.
- Add buffer to the project (not every task): 20–30% for familiar tasks, more for new technologies.
- Include vacations and holidays in the project calendar.
How to report an assessment#
- Let's give a range, not a dot: "4–6 weeks, more like 5."
- Name assumptions: "assuming the payment API is ready by the 10th."
- Review the assessment at each milestone and report changes immediately, not on the deadline day.
💬 What was your biggest score failure and why? Share in the comments.