How to Evaluate IT Projects and Avoid Double Deadlines

🌐 Machine-translated from Russian. Show original

"We'll do it in two weeks" — and two months later the project is still running. Mistakes in the estimates are almost always the same. Let's figure out how to avoid them.

In this part:

Why Grades Lie#

  • They only evaluate the code, forgetting about analysis, tests, reviews, deployments, documentation, and approvals.
  • They are evaluated under ideal conditions: no vacations, illnesses, urgent tasks, or meetings.
  • Uncertainty at the beginning is huge: at the start, the actual timeframe can differ from the estimate several times. As requirements are refined, the range narrows — so the estimate needs to be revised.

Decomposition#

The main tool: break the work down until each task is no more than 1–2 days. "Weekly" tasks are uncertainty, not evaluation.

Don't forget the tasks that are not visible in the TS:

  • setting up the environment and CI;
  • data migration and transfer;
  • integrations and testing them with the other side;
  • user training and documentation;
  • post-launch stabilization.

Three-point assessment (PERT)#

For each problem, there are three numbers: the optimistic (O), the most likely (M), and the pessimistic (P) estimate.

Expected time = (O + 4M + P) / 6

ProblemOMPExpected
Registration form1252.3 days
Integration with payments24125 days
Sales report11.531.7 days

The big difference between M and P is a risk signal: clarify such tasks first.

Evaluation by the team#

  • Planning poker: everyone evaluates independently, then discusses discrepancies. A multiplicity means people understand the task differently.
  • The one who will do it is evaluated, not the manager for them.

Buffer and calendar#

  • Convert ideal days into calendar days: a developer usually has 5–6 productive hours a day, not 8.
  • Add buffer to the project (not every task): 20–30% for familiar tasks, more for new technologies.
  • Include vacations and holidays in the project calendar.

How to report an assessment#

  • Let's give a range, not a dot: "4–6 weeks, more like 5."
  • Name assumptions: "assuming the payment API is ready by the 10th."
  • Review the assessment at each milestone and report changes immediately, not on the deadline day.

💬 What was your biggest score failure and why? Share in the comments.