ACS, part 5: installation — cables, power, locks, turnstiles, and commissioning

🌐 Machine-translated from Russian. Show original

In this part:

Cable part#

LineCableLimitations
Reader → controller (Wiegand)a multi-core signal cable, better shieldedusually up to 100–150 m, more precisely according to
Controller → controller (RS-485, OSDP)twisted pairup to 1200 m according to line
Controller → networktwisted pair Cat5e/6up to 100 m to switch
Power supply to the lockcable by the lock current and line lengthconsider voltage drop
  • Signal lines are separate from power lines.
  • Cables in the door and door frame — through the cable junction (flexible transition), otherwise they will wear out.
  • Marking each cable on both sides and a cable log.

Diet#

  • The power supply with battery is calculated based on the sum of currents: controller + readers + locks (the electromagnetic lock has constant current while the door is closed).
  • Battery life depends on the site's requirements (often several hours).
  • Separate power supply for the locks and electronics — interference from the locks does not knock down the controller.

Installing locks#

  • The electromagnetic lock is placed on the door frame, the counter bar on the door; the surfaces must fit tightly, otherwise the holding force drops sharply.
  • Electromechanical cuts into the door; check compatibility with the thickness and material of the door.
  • A close close is mandatory — without it, the door does not close completely.
  • The door opening sensor allows you to track "door is held open" and break-in.

Turnstiles#

  • Foundation or strong base, anchor fastening according to documentation.
  • Cables to the turnstile are in embedded pipes in the floor; plan them before finishing.
  • Evacuation routes: next to turnstiles — a gate or passage, unlocked by fire alarms and manually by a security post.
  • The readers are at a comfortable height, with clear input/output input.

Commissioning#

  1. Check the voltage levels on each device under load.
  2. Firmware updates for controllers and readers.
  3. Changing device and software factory passwords.
  4. Configuring doors, access levels, and schedules.
  5. Test of each door: entry by card, refusal by someone else's card, exit by button, door open alarm, battery operation.
  6. Fire unblocking test together with the fire safety officer — with an entry in the report.
  7. Training administrators and operators, transferring the system passport and passwords to the customer.

As-built documentation#

A plan with device locations, wiring diagrams, cable log, IP address list, logins (in secure storage), test report. Without this, the next contractor will start by "checking" the entire site.

Next — operation.